[mpas-developers] proposed order/timeline for MPAS-O commits
Ringler, Todd D
ringler at lanl.gov
Thu Mar 8 15:45:23 MST 2012
Hi All,
OK, it seems like we are back on track here and ready to move the trunk forward. Here is my proposed order/timeline. Let me know if there are any concerns/issues that I have missed.
1. Doug: FCT to trunk. This will not include all of the present options available for 2nd and 3rd order transport. Doug will make a new branch to re-implement those. Proposed time: Monday morning.
2. Doug: Trunk to GMVar. This will push the trunk out to Qingshan's isopycnal GM implementation. Proposed time: Monday afternoon.
3. Todd/Qingshan/Mark: Meet to finalize how to make sure GMVar does not break split explit. Proposed time: Meet sometime on Monday.
4. Todd/Qingshan/Mark: Test GMVar in various configurations (maybe using new test case suite). Proposed time: Tuesday/Wed/Thurs
5. Doug: Push GMVar to trunk. Proposed time: Thursday PM.
6. Doug: Make branch to re-implement "old" 2nd and 3rd order transport operators. Proposed time: Anytime after #5
7. Qinshan: Delete GMVar. Recreate GMVar. Proposed time: Anytime after #5
Seems like a full week to me .... so I will stop there.
Cheers,
Todd