Folks, apologies... the timeline given in the SOW that I sent out a bit
ago was incomplete. Here's the current, reasonably correct timeline:
Timeline
All dates/times are deadlines for deliverables. We encourage developers
to provide deliverables ahead of these dates if possible.
10/1/12 Developer begins work on app(s)
10/12/12 First app/feature review with HAO personnel
10/19/12 Second app/feature review with HAO personnel
11/2/12 Third app/feature review with HAO personnel
11/7/12 Basic app made available in app store(s), source code
provided to HAO
11/30/12 Fourth app/feature review with HAO personnel
12/14/12 Fifth app/feature review with HAO personnel
1/4/13 Final app/feature review with HAO personnel, source
provided to HAO, final version of app submitted to app store(s)
LJ